Affordable rent

123

Social rent

37

Shared ownership

85

You wanted homes to become available more quickly.

We streamlined the way the empty-property and lettings teams worked together, helping reduce the time taken to re-let homes.

New lettings

575

Time to re-let an empty property

26 days

Side of a small electric car with the fairhive logo and Blue, Green and Yellow tirangles on the car.

New builds delivered

We delivered 245 new homes during 2023/24. We also continued to let existing homes and improve their environmental performance. Our work included insulation, smart thermostats and other measures intended to improve energy efficiency and comfort.

New homes delivered : 245

Tarmac foot path with trees and shrubs on the left.

Our empty-property and lettings teams worked together to prepare homes for new residents and improve turnaround times.

Front on elevation of a new build brick flatted block.

South Court development

A brick-laying ceremony in February 2024 marked progress on a development of 20 flats and four houses at South Court in Aylesbury. Plans included electric heating and electric vehicle charging, with local shops and transport links within walking distance. The development was scheduled to welcome residents in spring 2025. Of the homes completed during 2023/24, ten achieved EPC A.

Semi-detached brick houses with brown concrete slat room and dark front doors.

Environmental home improvements

We installed 523 Switchee smart thermostats and recorded 199 EPC improvements. Our programme included insulation and heating upgrades, supported by the Social Housing Decarbonisation Fund and Warmfront. The published resident report records 123 environmental home improvements.

Homes receiving insulation works

266

New Switchee smart thermostats installed

523

Environmental home improvements

123

Energy Performance Certificate improvements

199